"T-623-2015
Oshawa Landfill Site Slope Stability Program located at 1640 Ritson Road North in Oshawa
The
Region of Durham is seeking qualified Contractors to provide slope
stabilization within the area of Seep B, adjacent to the Oshawa Landfill Site.
The proposed work program is being carried out the improve the slope stability
of the lands adjacent to the stream bank. It will involve the diversion of the
adjacent stream, to permit a gradual transition from the slope to the stream
bank, and re-grading the existing slope.
Construction
is expected to begin in August 2015, and should be completed within six (6)
weeks."
Further
information on the can be found in the Invitation to Tender posting,
https://www.durham.ca/biddingopportunities/SearchReadOnly.aspx or https://www.durham.ca/biddingopportunities/Attachment.aspx?id=47583&doc=Z&docType=pdf.